Posted on: January 11, 2018

Mid-February completion for Homestead Road

IMG_0575

PAHRUMP, Nev. - The Homestead Road Improvements Project is scheduled to be completed in mid-February.
The re-build project covers approximately 1 mile from Gamebird Road to Manse Road. Homestead has remained open during construction. There will continue to be periodic delays at the Homestead intersections at Gamebird and Manse roads, as well as at Jeane Avenue.
The January rain that brought nearly a 0.75 inch of rain to the area pushed the project a day. The unexpected relocation of some underground utilities has also pushed the end date for completion into mid-February.  
The Board of Nye County Commissioners awarded the $1.8 project to Pahrump-based Wulfenstein Construction during the board's regular meeting September 19, 2017. Road work began November 8, 2017.
The re-build project will run approximately 1 mile from Gamebird Road to Manse Road. Homestead will remain open during construction. There will be periodic delays at the Homestead intersections at Gamebird and Manse.
Working hours for construction will be Monday through Saturday, 6 a.m. to 4 p.m.
Nye County road crews placed electronic road signs at both ends of the project.
The project is funded by the Nye County Road Fund, which is supported by the county gas tax.

                                                                                                                                            #########